This is the November 2026 edition of our data center permit tracker. Since the October edition, three things changed in Charlotte, and all three show up in the record of who is allowed to build what.
On October 26, Charlotte City Council voted unanimously to extend its pause on new data centers to October 18, 2027. On November 4, Mecklenburg County permitted four more data halls at Digital Realty's Moores Chapel Road campus. And on November 11, WFAE reported a proposed county air permit for 242 diesel generators there.
$654.8M
Declared cost on building and upfit permits at Digital Realty's west Charlotte campus, March to November 2026
12
Data hall suites permitted at the campus, four of them on November 4, 2026
153
Data center permits in the offices TarSignal reads since January 2025, 44 of them since October 19
242
Diesel generators, 726 megawatts in all, in the proposed county air permit (WFAE)
Quick answers
Was Charlotte's data center moratorium extended?
Yes. On October 26, 2026, Charlotte City Council voted unanimously to extend its moratorium on new data centers to October 18, 2027. The first 150-day pause, approved in June, was due to end on November 5. It pauses the acceptance, processing and approval of applications for new data center projects; existing permits for data centers are unaffected.
How much is Digital Realty building in Charlotte?
Building and upfit permits at its campus on Moores Chapel Road in west Charlotte declare $654.8 million, from March to November 2026: a 1,294,518-square-foot shell, a $150.3 million powered base building upfit and 12 data hall upfits. Declared cost is what the applicant put on each permit, not the project's full cost.
How many generators will the Digital Realty Charlotte data center have?
A proposed Mecklenburg County air quality permit would allow Digital Realty to run 242 diesel generators, 726 megawatts in all, at the campus during blackouts, WFAE reported on November 11, 2026. The permit would allow over 100 tons of air pollution a year. Regulators hadn't decided as of that report.
Does the moratorium stop the Moores Chapel Road campus?
No. The city approved the rezoning before the moratorium, and existing data center permits are unaffected. Mecklenburg County issued permits for four more data halls there on November 4, 2026, during the moratorium.
Where can I see data center permits in North Carolina?
TarSignal's Permit Search shows every permit at an address, with the contractor named on each, for the North Carolina permit offices it reads. The table below links each data center address to its permits.
What changed since the October edition
- The moratorium was extended. Charlotte City Council voted unanimously on October 26 to extend its pause on new data centers to October 18, 2027. WFAE reported that existing permits for data centers are unaffected.
- An air permit is pending. A proposed Mecklenburg County air quality permit would allow Digital Realty to run 242 diesel generators, 726 megawatts in all, at the Moores Chapel Road campus during blackouts, and to emit over 100 tons of air pollution a year. As of WFAE's November 11 report, regulators hadn't decided.
- Four more data halls were permitted. Mecklenburg County issued upfit permits for suites 110, 120, 210 and 220 on November 4, declared at $166.1 million together.
I feel as though the only restriction that we have to being able to adopt some smart regulatory steps is the fact that we cannot downzone,
The council is looking to the General Assembly for new laws early in next year's session, WFAE reported. Until then, no new data center applications move in Charlotte, so for trades and suppliers the work on offer is the projects already permitted.
Digital Realty's Charlotte campus, month by month
| Month | million dollars declared on building and upfit permits |
|---|---|
| Mar | 9.3 |
| Apr | 0 |
| May | 151.1 |
| Jun | 0 |
| Jul | 246 |
| Aug | 41.1 |
| Sep | 41.1 |
| Oct | 0 |
| Nov | 166.2 |
The campus sits on Moores Chapel Road and Lakebrook Road, between I-85 and Wilkinson Boulevard. Its 1,294,518-square-foot shell permit was issued on May 29, the same day as a $150.3 million upfit permit labeled "CLT 13 PBB". Six data hall upfits followed in July, one on August 31, one on September 4 and four on November 4.
October brought only re-filed permits for suites already permitted, labeled RTAP, at the same declared values as the originals. We count each suite once, which is why October shows nothing new.
105
- Issued
- Jul 6, 2026
- Declared cost
- $39.8 million
115
- Issued
- Jul 6, 2026
- Declared cost
- $42.0 million
125
- Issued
- Jul 7, 2026
- Declared cost
- $40.8 million
205
- Issued
- Jul 7, 2026
- Declared cost
- $41.1 million
215
- Issued
- Jul 9, 2026
- Declared cost
- $41.2 million
225
- Issued
- Jul 9, 2026
- Declared cost
- $41.1 million
100
- Issued
- Aug 31, 2026
- Declared cost
- $41.1 million
200
- Issued
- Sep 4, 2026
- Declared cost
- $41.1 million
110
- Issued
- Nov 4, 2026
- Declared cost
- $41.7 million
120
- Issued
- Nov 4, 2026
- Declared cost
- $41.7 million
210
- Issued
- Nov 4, 2026
- Declared cost
- $41.7 million
220
- Issued
- Nov 4, 2026
- Declared cost
- $41.1 million
| Suite | Issued | Declared cost |
|---|---|---|
| 105 | Jul 6, 2026 | $39.8 million |
| 115 | Jul 6, 2026 | $42.0 million |
| 125 | Jul 7, 2026 | $40.8 million |
| 205 | Jul 7, 2026 | $41.1 million |
| 215 | Jul 9, 2026 | $41.2 million |
| 225 | Jul 9, 2026 | $41.1 million |
| 100 | Aug 31, 2026 | $41.1 million |
| 200 | Sep 4, 2026 | $41.1 million |
| 110 | Nov 4, 2026 | $41.7 million |
| 120 | Nov 4, 2026 | $41.7 million |
| 210 | Nov 4, 2026 | $41.7 million |
| 220 | Nov 4, 2026 | $41.1 million |
The suite numbers run 100 to 125 and 200 to 225, and all 12 now have permits. An October 20 electrical permit laid empty underground conduits for suites 130 and 140, the only sign in the record so far of halls beyond those 12.
Every hall comes with the same package: electrical, mechanical, plumbing and fire permits, and an electrical permit described as "Vista to transformer / MV duct bank". Brasfield & Gorrie is the contractor on nearly all of them. For electrical subs and gear suppliers, a new suite number in the record is the earliest public signal of the next package.
Uptown: the building the permits call CLT15
At 712 E 5th St, an owner named Digital Trade Street 2 LLC has 17 permits for a new data center building. Footing and foundation permits came on August 4. The shell permit, for 164,000 square feet, and a $15.0 million upfit permit labeled "CLT-15 PBB" were issued on October 12.
- Contractor: Whiting-Turner Contracting Company on the shell and upfit permits.
- Trade scopes named in the descriptions: electrical by Rosendin, controls by Schneider Electric, fire alarm by MSS.
- Next door: the same owner pulled demolition permits at 725 E Trade St in February and July 2026.
The permits use the same numbering as CLT13 at Moores Chapel Road. For trades that missed the west Charlotte packages, the uptown building is at the shell stage now, with the interior packages still ahead.
Every data center job in the permit records, since January 2025
Digital Realty campus: shell and 12 data-hall upfits
- Permits
- 113
- Declared cost
- $654.8 million
- Contractor on permit
- Brasfield & Gorrie
- Latest
- Nov 13, 2026
CLT15 uptown data center building (owner: Digital Trade Street 2 LLC)
- Permits
- 17
- Declared cost
- $15.0 million
- Contractor on permit
- Whiting-Turner
- Latest
- Oct 12, 2026
Duke University GPU data center, 13,173 sq ft
- Address
- 1811 Erwin Rd, Durham
- Permits
- 2
- Declared cost
- $10.3 million
- Contractor on permit
- LeChase Construction
- Latest
- Jul 27, 2026
NetApp Building 5: UPS and diesel generator
- Permits
- 1
- Declared cost
- $8.5 million
- Contractor on permit
- Choate Construction
- Latest
- Sep 19, 2025
Fidelity Investments RTP data center: UPS and interior work
- Permits
- 2
- Declared cost
- $7.6 million
- Contractor on permit
- Brasfield & Gorrie; McDonald York
- Latest
- Mar 5, 2026
CyrusOne DUR2: liquid cooling, busway, 1.5 MW lineup, material lifts
- Permits
- 9
- Declared cost
- $7.0 million
- Contractor on permit
- DPR Construction; Compu Dynamics; Ace/Avant Concrete
- Latest
- Oct 21, 2026
American Tower modular data center: addition and power module
- Address
- 6011 Chapel Hill Rd, Raleigh
- Permits
- 3
- Declared cost
- $1.1 million
- Contractor on permit
- HPM Contracting
- Latest
- Aug 13, 2026
| Project | Address | Permits | Declared cost | Contractor on permit | Latest |
|---|---|---|---|---|---|
| Digital Realty campus: shell and 12 data-hall upfits | 12925 Moores Chapel Rd and 9505 Lakebrook Rd, Charlotte 28214 | 113 | $654.8 million | Brasfield & Gorrie | Nov 13, 2026 |
| CLT15 uptown data center building (owner: Digital Trade Street 2 LLC) | 712 E 5th St, Charlotte 28202 | 17 | $15.0 million | Whiting-Turner | Oct 12, 2026 |
| Duke University GPU data center, 13,173 sq ft | 1811 Erwin Rd, Durham | 2 | $10.3 million | LeChase Construction | Jul 27, 2026 |
| NetApp Building 5: UPS and diesel generator | 6741 Louis Stephens Dr, Morrisville 27560 | 1 | $8.5 million | Choate Construction | Sep 19, 2025 |
| Fidelity Investments RTP data center: UPS and interior work | 7133 Louis Stephens Dr, Morrisville 27560 | 2 | $7.6 million | Brasfield & Gorrie; McDonald York | Mar 5, 2026 |
| CyrusOne DUR2: liquid cooling, busway, 1.5 MW lineup, material lifts | 2223 Northeast Creek Pkwy, Durham | 9 | $7.0 million | DPR Construction; Compu Dynamics; Ace/Avant Concrete | Oct 21, 2026 |
| American Tower modular data center: addition and power module | 6011 Chapel Hill Rd, Raleigh | 3 | $1.1 million | HPM Contracting | Aug 13, 2026 |
Outside Charlotte, the one new job since October is at CyrusOne's Durham site: a $1.0 million permit on October 21 for interior alterations for new material lifts at its data halls. Elsewhere the work is still power and cooling inside existing buildings, bid one package at a time.
How long the last gate takes
Town of Morrisville
- Median days
- 44
- Slowest 10% over
- 62
- Permits
- 7
Gaston County
- Median days
- 94
- Slowest 10% over
- 170
- Permits
- 21
Wake County
- Median days
- 102
- Slowest 10% over
- 192
- Permits
- 34
High Point
- Median days
- 127
- Slowest 10% over
- 209
- Permits
- 18
City of Raleigh
- Median days
- 134
- Slowest 10% over
- 335
- Permits
- 81
City of Greensboro
- Median days
- 136
- Slowest 10% over
- 250
- Permits
- 9
| Office | Median days | Slowest 10% over | Permits |
|---|---|---|---|
| Town of Morrisville | 44 | 62 | 7 |
| Gaston County | 94 | 170 | 21 |
| Wake County | 102 | 192 | 34 |
| High Point | 127 | 209 | 18 |
| City of Raleigh | 134 | 335 | 81 |
| City of Greensboro | 136 | 250 | 9 |
Big permits go through full plan review, often in several rounds, and an office's clock usually keeps running while plans go back for corrections. Mecklenburg County and Durham don't publish application dates in the records TarSignal reads, so the Charlotte and Durham jobs can't be timed this way.
Where TarSignal fits
- Subcontractors and suppliers: look up a campus address in Permit Search to see every permit filed there, with the contractors named on each, then search by contractor (Brasfield & Gorrie, Whiting-Turner, DPR) to find their other North Carolina jobs.
- Project Alerts (Pro): a daily email of new permits in the counties, towns and trades you choose, with a minimum project value, so the next data hall upfit reaches you the morning after we read it.
- Analysts, utilities and investors: the Data & API plan delivers the same permit records by API or bulk export, for tracking the buildout county by county.
How these numbers were counted
- Data center permits are those whose description names a data center or data hall, plus every permit at the campuses in the table, issued or applied for from January 1, 2025, to November 26, 2026, in the permit offices TarSignal reads. Withdrawn permits and an unrelated event permit at the Duke address are left out.
- Declared cost is the construction value the applicant put on the permit, not the project's full cost. At the Charlotte campus, the $654.8 million is the building, shell and upfit permits; trade permits are left out, and permits re-filed for a suite already permitted (labeled RTAP) are counted once. Counted the same way, the October edition's $488.7 million covered March to September.
- Counties outside TarSignal's coverage aren't in these counts. The moratorium, the air permit and the council's plans come from the WFAE and WBTV reports listed below, not from permit records.
Sources
- TarSignal: Permits are the brake on the AI data center buildout (October 2026 edition)
- WFAE: Charlotte data center could get backup power from 242 diesel generators, November 11, 2026
- WFAE: Charlotte extends its data center moratorium for 11 months, October 27, 2026
- WBTV: Data center moratorium extended in city of Charlotte: What to know
- TarSignal: Data center construction phases, from the permit record: how Digital Realty's Charlotte campus is being built
- TarSignal: North Carolina's share of the data center build-out, and the trades it pulls in
- TarSignal permit records, January 2025 to November 26, 2026
- Charlotte and Mecklenburg County permits in TarSignal