The largest construction projects in North Carolina: what's permitted, what's in review, and what's only announced

Omni's $308.2 million Raleigh hotel has its building permit. Spark LS's $158.5 million Origin 3 upfit in Morrisville has been in review for six weeks. JetZero's $4.7 billion Greensboro aircraft plant has no factory permit yet, because about a year of grading comes first. North Carolina's biggest jobs, sorted by where each one stands in the permit record.

On June 15, 2026, JetZero broke ground on a $4.7 billion aircraft factory at Piedmont Triad International Airport in Greensboro. A groundbreaking isn't a building permit, though, and for the contractors and suppliers who will do the work, the difference matters. This article sorts North Carolina's largest projects by where each one stands in the permit record: cleared to build, filed and waiting, or announced with little or nothing permitted yet.

$308.2M

Omni Raleigh hotel: the largest building permit filed in the last 12 months in any office TarSignal reads. Issued July 10, 2026.

$158.5M

Origin 3 tenant upfit at Spark LS in Morrisville, in review since September 22, 2026

337 days

How long RDU's $83.0 million Terminal 2 north expansion package has been in review at Wake County

$4.7B

JetZero's announced Greensboro plant. No permit for the factory building has been filed yet.

Quick answers

What are the largest construction projects in North Carolina right now?

By announced investment, JetZero's $4.7 billion aircraft plant in Greensboro and Novo Nordisk's $4.1 billion fill-finish plant in Clayton. By the value on a single building permit filed in the last 12 months, the Omni Raleigh hotel ($308.2 million), followed by Spark LS's Origin 3 upfit in Morrisville ($158.5 million, still in review) and the shell of Digital Realty's west Charlotte data center campus ($150.3 million).

Has JetZero started construction in Greensboro?

JetZero broke ground on June 15, 2026. ENR reported that mass grading was expected to begin by August or September and continue for about a year before major vertical construction. As of November 3, 2026, no permit for the factory building appears in the City of Greensboro's or Guilford County's records. The City of Greensboro has issued permits for a $13 million office renovation at 725 N Regional Rd, where a July mechanical permit names Jet Zero.

When will the Omni hotel in Raleigh open?

ABC11 reported that Omni expects the work to be completed by the fourth quarter of 2028. Construction started in February 2026, and the City of Raleigh issued the hotel's $308.2 million building permit on July 10, 2026, naming Brasfield & Gorrie.

What is being built at Spark LS in Morrisville?

In December 2025 the campus's owners announced leases of more than 1.27 million sq ft to an undisclosed manufacturer: upfits of more than 400,000 sq ft of existing buildings, starting in early 2026, and a new 866,000 sq ft facility with structured parking. Morrisville has issued upfit permits for the Origin 1 and Origin 2 buildings, and a $158.5 million upfit for Origin 3 is in review.

What does 'In Review' mean on a building permit?

The office has the application and its plan reviewers haven't approved it yet. Work covered by that permit can't start. One exception to watch: the City of Raleigh's record for the Omni hotel shows an issue date of July 10, 2026, while its current status reads In Review, so check the issue date as well as the status.

Cleared to build: the largest permits already issued

These projects have their main building permits, so the general contractor is named and the work is buying trades and materials. The table lists each one's largest permit. Where an office records several big permits for one job, the note says so.

The largest issued building permits filed November 2025 to October 2026, by project. Value is the declared value on the project's largest permit unless noted. Each project opens its permits in Permit Search.

Download the data (CSV)

Value on each project's largest issued building permit, November 2025 to October 2026, in millions of dollars
  1. Omni Raleigh hotel$308.2M
  2. Digital Realty CLT13 (shell + PBB)$150.3M
  3. North Mecklenburg High School$134.1M
  4. CMS building, 700 E MLK Jr Blvd$97.9M
  5. Lenovo Center alterations$89.1M
  6. 2000 Science Dr fit-out$75.2M
  7. Charlotte Hornets PEC shell$70.3M
  8. Lindley Elementary$68.3M
  9. Sumner Elementary$61.4M
  10. Gastonia Industrial$59.7M

Values are Millions of dollars on the largest permit.

Download the data (CSV)

The Omni shows how far site work can run ahead of the building permit. ABC11 reported on February 17, 2026, that crews were ripping up the parking lot on the site, and the city issued a permit for construction trailers on March 5. The $308.2 million building permit, filed December 5, 2025, was issued 217 days later. A permit for the foundation of the second tower crane followed on August 12.

For a sub, the issued list is where the buying is. The general contractor on each of these jobs is choosing trades now, and the trade permits that follow name who won.

Filed and waiting: big permits still in review

These permits are filed and not yet issued. The applicant and builder are known, but the permitted work can't start. Days waiting are counted to November 4, 2026.

Building permits of $20 million or more filed November 2025 to October 2026 and not issued as of November 3, 2026, with the office's status. Each project opens its permits in Permit Search.

Download the data (CSV)

RDU is a case where construction and review run side by side. ABC11 reported that the airport's $2.5 billion Transform RDU program began at Terminal 2 with a temporary wall that will stay up for two years. Meanwhile, Wake County's record for the $83.0 million north expansion package has read In Review since December 2, 2025. Big programs are permitted in packages, so one package waiting doesn't mean the site is idle.

Origin 3 is the one to watch in Morrisville. It's the largest permit waiting anywhere in our records, and its builder is already working next door on Origin 1 and Origin 2.

Announced: the biggest numbers, and what's permitted so far

The largest announcements in the state run into the billions. In the permit record, each one is at a different stage.

Major announced projects in North Carolina, what their announcements say, and what the permit records TarSignal reads show as of November 3, 2026. Sources are listed at the end.

Download the data (CSV)

This could be upwards of 7 or 8 million cubic yards of earth to move.
Kevin Baker, Executive director of the Piedmont Triad Airport Authority — ENR

JetZero's first work is the airport authority's. ENR reported that the authority's job is to deliver a construction-ready site to the edge of JetZero's leasehold, with Jacobs engineering the grading, and that JetZero had chosen its construction team but contracts were still being finalized. So the factory's building permits are still ahead. For site contractors, the grading is the job now. For everyone else, the trigger to watch is the first building permit for the campus.

Novo Nordisk is much further along. At 2641 Powhatan Rd, where Novo Nordisk Pharmaceutical and BE&K Building Group are applicants, Johnston County issued 66 of 86 permits between April 2024 and June 2025, and only eight in the last 12 months. That's what the record looks like once a project's main permits are in hand.

0102030Q4 2023Q1 2024Q2 2024Q3 2024Q4 2024Q1 2025Q2 2025Q3 2025Q4 2025Q1 2026Q2 2026Q3 2026
Permits issued each quarter at 2641 Powhatan Rd, Clayton (Johnston County), where BE&K Building Group and Novo Nordisk Pharmaceutical are applicants. Highlighted: the peak, July to September 2024.
Permits issued each quarter at 2641 Powhatan Rd, Clayton (Johnston County), where BE&K Building Group and Novo Nordisk Pharmaceutical are applicants. Highlighted: the peak, July to September 2024.
MonthPermits issued
Q4 20235
Q1 20247
Q2 202411
Q3 202428
Q4 20244
Q1 202514
Q2 20259
Q3 20250
Q4 20251
Q1 20266
Q2 20260
Q3 20261

Download the data (CSV)

What it means for each trade

  • Site, grading and utility contractors: JetZero's site is being graded by the Piedmont Triad Airport Authority, which puts the earthwork at upwards of 7 or 8 million cubic yards. Everyone else's trigger comes after that.
  • Electrical, mechanical and plumbing subs: the issued jobs are where trade permits come next. At Digital Realty's west Charlotte campus, each data hall suite came with its own electrical, mechanical and plumbing permits.
  • Fire protection, finishes and specialty trades: Origin 3's $158.5 million upfit and RDU's Terminal 2 packages are the large interior jobs still in review. Their builders, Brasfield & Gorrie and Balfour Beatty, are already named.
  • Suppliers and distributors: the general contractors named here repeat. Brasfield & Gorrie is on the Omni hotel, the Spark LS buildings and Digital Realty's Charlotte campus, so one account covers several of the state's largest jobs.

For a homeowner or a small sub, the biggest jobs matter less directly. They pull in labor across a region, so a crew booked on a hotel tower or a data hall isn't free for a remodel.

What this article doesn't cover

Large projects also need approvals that aren't building permits: rezonings, state air and water permits, and utility connections. Those aren't in the records TarSignal reads, and we haven't listed any we couldn't source. The statuses here are each office's own, as of November 3, 2026, and offices use different words for the same stage.

Where to find these permits in TarSignal

  • Permit Search: search an address from the tables to see every permit filed there, with the builder, the trade contractors and the status.
  • Project Alerts: get new permits in your trade and counties by email each morning, sorted Hot, Warm and Cold, so the next big filing reaches you the day it's posted.
  • Permit Analytics: see which offices and categories are moving, to spot the next cluster of big jobs.

How these numbers were counted

We took every permit with a declared value of $20 million or more filed November 1, 2025, to October 31, 2026, in the offices TarSignal reads, by filing date where the office records one and issue date where it doesn't. We left out Brunswick, Durham and New Hanover, which compute some values from fixed cost tables, and Johnston County permits we couldn't tie to a named project, because that county publishes no work description. We grouped permits into projects by address, owner of record and project name, and listed each project's largest permit.

  • Digital Realty's $494.4 million is the total on 65 permits through October 23, 2026, not counting revisions, from our article on the campus's construction phases.
  • At 2641 Powhatan Rd, the same value often appears on several of Johnston County's permits, so we count permits there and don't add up their values.
  • Siemens Energy's 59 permits are those with Siemens Energy as owner of record; the $30.7 million is their declared total.
  • We name an occupant only where the permit, the owner of record or a cited source does. The Origin buildings are Spark LS's own names for its buildings.
  • Announced figures are the companies' and agencies' own, from the sources below. We haven't estimated anything beyond them.