Commercial8 min read

North Carolina ends parking minimums on January 1, 2027: what a parking deck costs in NC permits

From January 1, 2027, most North Carolina cities and counties can no longer require a minimum number of parking spaces. What the law says, where it doesn't apply, and what parking costs in 12 months of permits: five parking decks worth $109.7 million, at $65 to $150 a square foot and about $44,600 a space.

On January 1, 2027, most local governments in North Carolina lose the power to require a minimum number of parking spaces. Session Law 2026-39 (House Bill 162), signed on July 6, 2026, bars zoning and development rules from setting a minimum number of off-street spaces for any development or structure, whatever its use. Twenty coastal counties are left out.

Parking is one of the most expensive things a zoning code can require. We went through 12 months of building permits from the 23 North Carolina permit offices TarSignal reads to see what it costs to build here, who builds it, and what the change means for the trades that pour, pave, light and stripe it.

Jan 1, 2027

The day most NC local governments can no longer require a minimum number of parking spaces

$109.7M

Declared value of the five parking decks filed or issued in the 12 months to October 31, 2026

$44,600

Per space for a 393-space hospital parking deck in Gastonia, from its permit

$65–$150

Per square foot for the four decks whose permits give both a value and a size

Quick answers

When do parking minimums end in North Carolina?

January 1, 2027. That is when Section 1 of Session Law 2026-39 (House Bill 162) takes effect. From then, a zoning or development regulation can't require an off-street parking lot to meet a minimum number of spaces per development or structure, regardless of occupancy or use.

Does the law apply everywhere in North Carolina?

No. It doesn't apply to local governments in the coastal area defined in G.S. 113A-103, which the statute lists as 20 counties, including Brunswick, New Hanover and Onslow. Inside those counties the ban still covers historic districts, landmarks and properties on the National Register study list.

Can a developer still build parking after January 1, 2027?

Yes. The law only stops local governments from requiring a minimum number of spaces. An owner, lender or tenant can still ask for as much parking as they want, and the law says nothing about parking maximums.

How much does a parking deck cost per space in North Carolina?

The one permit in our records that states both a value and a space count is a 3-story, 393-space hospital deck in Gastonia with a declared value of $17,514,000, or about $44,600 a space. Four decks filed or issued in the 12 months to October 31, 2026 came to $65, $107, $119 and $150 a square foot.

How much does a surface parking lot cost per space?

One example from the permits: a 28-space staff parking lot expansion in Durham, issued October 13, 2026, with a declared value of $518,542, or about $18,500 a space. That includes grading, paving, drainage and striping on a small job.

Does House Bill 162 change stormwater rules?

Yes. Since July 6, 2026, stormwater programs can't require new or bigger controls for built-upon area that already exists on a site, and each local government with a stormwater program has 12 months to amend its ordinance to match.

What the parking law says

The law adds one line to the list of things a zoning or development regulation may not do (G.S. 160D-702(c)): require an off-street parking lot "to meet a minimum number of parking spaces per development or structure, regardless of occupancy or use." It covers every kind of project, from apartments to shopping centers. It takes effect on January 1, 2027.

  • Where it doesn't apply: local governments in the coastal area, as G.S. 113A-103 defines it. The statute lists 20 counties, among them Brunswick, New Hanover and Onslow.
  • The exception inside the coast: the ban does apply there to historic districts, designated landmarks and properties on the National Register study list.
  • What was already law: a local rule can't require a space larger than 9 by 20 feet, unless it's for handicap, parallel or diagonal parking.
  • What it leaves alone: parking maximums, and an owner's own choice to build parking.
This bill gives North Carolina another tool in the toolbox to build more homes and make housing more affordable.
Josh Stein, Governor of North Carolina — Office of the Governor

Raleigh and Durham had already dropped their parking minimums before the state acted, WUNC reported in July. For a builder working in those two cities, nothing changes in January. Everywhere else outside the coast, the required-spaces table in the local code stops binding new projects.

What a parking deck costs in NC permits

Permits for five parking decks were filed or issued in the 12 months to October 31, 2026, in Morrisville, Charlotte and Gastonia. Together they declare $109.7 million of construction. One serves a high school and one a cancer center, and two are in Charlotte.

  • Project Roanoke Parking Deck 2, McCrimmon Pkwy

    Permit office
    Morrisville
    Declared value
    $34.0M
    Size
    522,574 sq ft
    Contractor on the permit
    Brasfield & Gorrie
  • 3-story deck for Morrisville High School

    Permit office
    Wake County
    Declared value
    $26.9M
    Size
    179,345 sq ft
    Contractor on the permit
    T.A. Loving Company
  • 7-story garage, Periwinkle Hill Ave, Charlotte

    Permit office
    Mecklenburg County
    Declared value
    $24.9M
    Size
    233,179 sq ft
    Contractor on the permit
    Arlington Construction
  • 3-story, 393-space deck, CaroMont Cancer Center, Gastonia

    Permit office
    Gaston County
    Declared value
    $17.5M
    Size
    About 147,000 sq ft
    Contractor on the permit
    Not named
  • 7-floor precast deck, Central Ave, Charlotte (installation)

    Permit office
    Mecklenburg County
    Declared value
    $6.4M
    Size
    Not comparable
    Contractor on the permit
    Fortune-Johnson
Parking decks in building permits filed or issued November 1, 2025 to October 31, 2026, with the value and size each permit declares. The Central Avenue permit covers installing the precast deck only. Each office opens its permit page.

Download the data (CSV)

Four of the five give a value and a size for the whole deck. They work out to $65 to $150 a square foot. The Gastonia permit is the only one that also says how many cars the deck holds: 393 spaces in about 147,000 square feet, or about 374 square feet a car once ramps and aisles are counted.

Declared value per square foot for the four parking decks whose permits give both, November 2025 to October 2026.
  1. Morrisville HS deck$150
  2. CaroMont deck, Gastonia$119
  3. Periwinkle Hill, Charlotte$107
  4. Project Roanoke Deck 2$65

Values are dollars per square foot.

Download the data (CSV)

At $17,514,000 for 393 spaces, the Gastonia deck costs about $44,600 a space. That is above the $30,000 to $40,000 a space the Commercial Real Estate Development Association estimates, as WUNC reported. For concrete, precast and post-tension subs, each required space a developer no longer has to build is a real piece of a budget, and each deck that still gets built is an eight-figure job.

Surface lots barely show up in permits

Surface lots leave little trace in building permit records. In the same 12 months, only 105 permits across the offices we read mention a parking lot at all, and most are for something done on a lot that already exists.

  • Lighting: about a dozen permits to add or replace lot lights, from a single pole to site lighting for a whole venue.
  • EV chargers: ten permits, the largest a $1,253,888 charging station project in a Greensboro store's lot.
  • New or bigger lots: a handful, including a $1,296,954 lot expansion at the Greensboro Science Center and a 28-space, $518,542 staff lot expansion in Durham.
  • Everything else: temporary sales centers, tents, food trucks and construction trailers set up on a lot.

How much parking a new store builds today shows up in the building permit instead. A grocery store permitted in Charlotte in September 2025 describes a 112,162 square foot building with parking for 660 cars, about 5.9 spaces per 1,000 square feet. For paving and striping contractors, that ratio is the number to watch on site plans after January, because the permit records won't show it changing.

The stormwater change is already in effect

The second half of the law took effect when it was signed, on July 6, 2026. Stormwater programs can no longer require new or increased controls for built-upon area that already exists on a site. When a site is redeveloped, the old pavement and roofs count square foot for square foot against the area that needs controls, whether they're demolished, moved or left in place.

Each local government with a stormwater program has 12 months from that date to amend its ordinance, and the law makes a conflicting ordinance void and unenforceable. Local governments may also offer incentives, such as waived fees, for projects that go beyond the required controls.

There's properties that have sat vacant for years, they recently got rid of their minimums last year, and have seen a wave of reinvestment and redevelopment happening there
Ryan Carter, policy director at Catawba Riverkeeper, on the town of Cramerton — WUNC News

For demolition, grading and site contractors, the two halves point the same way: older commercial sites with more pavement than a new use needs get cheaper to rebuild.

What it means for each trade

  • General contractors and developers: parking counts on projects approved after January 1, 2027 are set by the owner, lender and tenants. Ask early how many spaces the pro forma assumes, because the code will no longer answer it.
  • Concrete, precast and post-tension subs: decks are built where the owner needs the spaces whatever the code says. Two of the five in the last 12 months serve a high school and a cancer center.
  • Paving, striping and site contractors: a lot seldom gets a building permit of its own. Follow new commercial building permits to find the general contractor while the site package is still being bought.
  • Electricians: lot lighting and EV chargers are the parking work that does get its own permit, about 22 of them in 12 months.
  • Suppliers: a required space that isn't built is asphalt, stone, pipe and striping that isn't ordered. Decks, at $65 to $150 a square foot, are unaffected where the owner wants them.

Find parking and site work in TarSignal

Permit Search finds parking decks by searching permit descriptions for "parking deck" or "parking garage" in any office we read, with the contractor and declared value on each. Project Alerts sends new commercial building permits in your area each morning, which is where a surface lot first appears: in the description of the building it serves.

How these numbers were counted

  • Records: building permits from the 23 North Carolina permit offices TarSignal reads, dated November 1, 2025 to October 31, 2026 by filing date where the office records one and by issue date where it doesn't (Mecklenburg County and Durham).
  • Parking decks: permits for a new, stand-alone parking deck or garage with a declared value of $1 million or more, found by description ("parking deck", "parking garage", "parking structure") and read one by one. Trade permits, repairs, demolitions and buildings that only include a garage were left out, so a deck permitted as part of an apartment or office building isn't counted.
  • Values and sizes are what each permit declares. The Central Avenue permit covers the precast installation only, so it's in the total but not in the cost per square foot. The Gastonia deck's size and spaces are from its description. Its permit was filed August 4, 2026 and issued November 6.
  • Cost per square foot is the declared value divided by the declared size. Offices record these differently, and a declared value isn't a bid or a final cost.
  • Parking lots: permits whose description mentions a parking lot, without withdrawn, voided, cancelled or denied permits. The groups were sorted by hand from the descriptions, so they're approximate. Coverage in some offices grew during the period, so no comparison is made with earlier years.
  • The law is quoted from Session Law 2026-39. The coastal counties are those G.S. 113A-103 lists as designated on July 1, 2012. The cost estimate and the note on Raleigh and Durham are as WUNC News reported them on July 2, 2026.